Claim Digger Limitations

Primavera SchedulingClaim Digger is a convenient tool inside Primavera P6 for comparing schedule files to determine what changes have been made. But there are limitations to what Claim Digger can tell us about a revised file. Experienced Primavera users will recall that Claim Digger used to be a third-party program used to analyze Primavera P3 files. When Claim Digger was incorporated into Primavera P6 several years ago the functionality changed in ways that were both good and bad. Being able to export to HTML format is nice, but having the durations (including float and lags) displayed in hours is inconvenient on schedules with durations that are shown in days.

There are third-party software programs that can do much more than Claim Digger. Still, if you think that Primavera P6 costs as much as having a baby then anything that is “free” will be the most desirable option. So most of us will have to get by with Claim Digger until money starts growing on trees.


Note: in Version 16.1 of Primavera P6 Claim Digger is now called Schedule Comparison and is accessed from the Visualizer program. You will find Scheduler Comparison in the same location (Tools) as Claim Digger but clicking on this button will launch the Visualizer program.


The biggest limitation in Claim Digger has to do with calendars. Here are two scenarios where Claim Diggers will let you down:

  1. Changes made to a calendar, such as revisions to the number of hours per day, days per week, holidays, etc. are not picked up by Claim Digger
  2. Changing the calendar on an activity from Global to Project (or vice versa) is not picked up if both calendars have the same exact name

Indeed, Claim Digger will tell us nothing about calendars other than whether the name of the calendar is different. To demonstrate this for myself I created a Project calendar called “Standard” that is a copy of a Global calendar with the same name. I assigned the Global calendar to all of the activities in a sample project. After creating a baseline (copy) of this project I switched the calendar on the activities in the current project to the Project calendar. Claim Digger did not report any changes to calendars.

I then changed the name of my Project calendar in the current project to “Standard Days” and re-ran Claim Digger. As I expected, Claim Digger reported that I had changed the calendar. Yet other than the name, it was still the same Project calendar. I hadn’t changed anything else. In other words, a false positive.

Owners often run Claim Digger (or ask for the results) so anything that suggests a change when in fact no change was made creates unnecessary confusion. Conversely, a sneaky scheduler could block out additional days in the calendar to coincide with an owner-caused delay in order to exaggerate the impact. An experienced scheduler should be able to figure out if there are any shenanigans going on, but the reality is that P6 is chock-full of hidden traps for the uninitiated.

While we are on the subject, I often refer to myself as a “Primavera P6 Scheduler” because there are in fact specific techniques to scheduling projects with Primavera P6. Case in point: Microsoft Project does not allow two relationships between the same two activities, while in Primavera P6 this is perfectly acceptable. A good scheduler with poor Primavera P6 skills can still make a lot of mistakes because of their unfamiliarity with the program. For the same reason, I tend to be very cautious in Microsoft Project because it is not my bread and butter.

I started using Primavera software in 1987 so in my mind the rules that I observe have almost always been specific to one particular program. Prior to 1987 the software I used was proprietary and followed basic Critical Path Method rules. But CPM does not teach you about Activity Codes, Resource Leveling, and so many other things that are now possible because of software any more than an accountant would automatically know how to create a macro in Microsoft Excel.

“Old-school” schedulers who refuse to stay current on scheduling software get no sympathy from me. I started with proprietary scheduling software, learned Primavera P3, followed by Primavera SureTrak, Primavera Primavera P6, Primavera Contractor, and Primavera P6 EPPM. Not to mention all of the other programs like Microsoft Office that I have had to learn over the years. I had to learn WordPress just to type this silly blog!