Ah, but there is a trade-off for simplicity! Oracle’s Application Programming Interfaces (APIs) are not compatible with SQLite. This is something Oracle intends to fix in a future P6 release or patch. APIs are the building blocks of many software programs, and while it is not something most of us would ever realize, Oracle’s Claim Digger is an API. So Claim Digger is not accessible when using SQLite. For me, that is a deal-breaker. I use Claim Digger nearly every day to analyze files. In some situations my clients have more than one version of a baseline schedule or update on their server and they no longer remember why. If some of these files are in fact identical we can delete them without any concern. At the very least, Claim Digger will tell us what the differences are. Most owners also expect contractors to explain what changes were made during the update process, and the Claim Digger report usually suffices.
Claim Digger does have some limitations, which I will discuss in a future blog, and there are third-party programs that are more powerful. However, Claim Digger is included with P6 so it is a tool that all users have access to without spending more money. I will accept free help anytime!
Also, because SQLite is truly a single-user environment, there are several other restrictions:
- There are no User or Security Profiles, as there can only be one user
- All projects are opened in Shared mode; Read Only and Exclusive modes are disabled
- Sending e-mail notifications of Project Issues is not supported
- Advanced import options are disabled for projects in XML format
- Check In and Check Out of projects are disabled
- There are no options to save data for All Users or Another User (layouts, etc.)
- Job Services is not supported; Jobs cannot be scheduled
- Update Baseline and Risk Analysis are not supported